Case Study: Thunderhorse Subsea PLET Reconnect Project
Location: Offshore, 150 miles south of New Orleans in the Gulf of Mexico
Operator: BP
During the rehabilitation of the Thunderhorse field, problems were discovered with some of the welds in the subsea manifolds and PLET’s, resulting in them having to be brought to the surface for inspection and remedial repairs.
Sureclean Scope
Provide manpower and equipment for the removal of existing field joint
coating using Ultra High Pressure Water Jetting Cold Cutting
application to facilitate NDT inspection and repairs.
The Technical Challenge
Engineering a solution which safely, effectively and efficiently
removed the coating (4 inch layer of composite material
(polypropylene), without damaging the flow line and importantly
contained all water and debris arising from the operation.
Restrictions / Considerations
1) Under no circumstances could we, when removing the composite, make
even the slightest “cut” into the actual flow line sections.
2) The area in which we had to execute the project was “environmentally
sensitive”, meaning we had to ensure 100% catchment and containment of
all water and debris arising from the operation.
3) Critical Path Timeline.
4) The humidity in the work area during the operations reached 45
degrees at times, so it was crucial our operative’s welfare was taken
into account during the “Project-planning” regimes.
Project
Completed in two phases, phase 1 was effectively the development phase
which involved 6 months of extensive trials and technology development
to engineer and perfect a cutting solution at the HMC welding facility
in Vlissingen, the Netherlands.
Phase 2
Phase 2 was the live operations, offshore in the Gulf of Mexico, where
the flow lines sections would be lifted onto either the Thialf (the
largest Deepwater Construction Vessel in the world capable of a tandem
lift of 14,200 t operated by Heerema Marine Contractors) or the Balder
( a Deepwater Construction Vessel capable of a tandem lift of 6,300 t,
operated by Heerema Marine Contractors ) from depths of up to 1900
metres, to allow the removal of sections of the composite, exposing the
welds for NDT inspection, remedial repairs, re-coating and re-use as
appropriate.
Key Facts
The project was successfully completed without safety or environmental incident
Success of the engineered cutting solution
Involved 16 Sureclean personnel
Lasted for 14 months (from Feb 07 to April 08)
Provided turnover of $2.4 million USD to Sureclean
|