Case Study: Rowan Drilling
Location: Rowan Gorilla VI,Dry Docks, Dundee
During a scheduled shipyard visit we were initially contracted to remove all residues and clean all tanks onboard to allow inspection.
Sureclean Scope
Primary scope of work was to provide the necessary manpower and equipment for the removal of all residues and cleaning of all tanks onboard the Rowan Gorilla VI; allowing inspection and remedial repairs to be carried out. Scope of works were extended to include:
- Removal of all residues and cleaning of all tanks
- Surveying, Camera Inspection and cleaning of entire HVAC system
- Surface Preparation and Painting of hull
- HP Jetting and vessel entry spread for the chlorination of two pot water tanks
Technical Challenge
Logistics associated with resourcing, planning and managing project growth, within a critical path. Manning profile grew from an original plan of 5 personnel, peaking at 18 personnel with equipment requirements increasing accordingly.
Restrictions/Considerations
- Timeline - Critical Path Project
- Project Management, resourcing, planning and scheduling
- Conflicting activities
- Hazardous Environment - Confined Space Entry Working, access and egress
- Waste containment and transfer
- Containment and disposal of paint chippings
- Safe use of hazardous substances
Key Achievements
- Project completed on time
- Project scope of work extended with Sureclean available at short notice
- Sureclean personnel regularly willing to help Rowan with jobs out with the work scope
Additional Information
Sureclean’s ethos of providing trained ‘multi-disciplined’ personnel provided a timely and cost effective solution allowing the client to optimise work completed. The integrated approach of working together adopted by all contractors involved in the project contributed to its overall success. Involved up to 18 Sureclean personnel, dayshift and nightshift working.
|