AIB Wall Panel Removal at Nairn Academy |
Case Study: AIB Wall Panel Removal
Location: Nairn Academy, Scotland
Client: Highland Council
Removal of AIB wall panel for Highland Council at Nairn Academy
Sureclean Scope
- AIB Wall Panel removal for Highland Council at Nairn Academy
- 6 personnel employed over 15 days
Technical Challenges
- Octagonal dining room area made enclosure of building a very complex operation
- Ensuring correct equipment / resources were available when required at different periods throughout the operation
Restrictions
To ensure that re-fitting works by others could be completed by end of the School Summer Holidays this project was completed within a tight schedule.
Key Achievements
- Job completed safely with no accidents or incidents
- Client kept informed of progress throughout works and advised of additional works which were required during project which were unforeseen
Photo Gallery
|